Dunn's Corners Fire Department · Westerly & Charlestown, R.I.

DCFD Training Building - Phase 1

Print this story (opens in a new tab)News RSS feed (opens in a new tab)Share on Facebook (opens in a new window)Share on X (opens in a new window)Add a comment

By Firefighter Chris Wells
November 5, 2008

For those of you who do not already know; The DCFD has recently gotten the approval to construct a non-burn training facility in the back of Station 2 in Charlestown. This training building will provide the department with the ability to train whenever and on any subject from our very own station.

The "building" itself is mainly comprised of a 8'x8'x40' cargo shipping container. The container was recently purchased and delivered to the back field at Station 2. Phase 1 of the project was recently completed which involved the building of the roof portion. The roof was built by the department's very own Lieutenant Carl Johnson. This roof will be used for roof operations as well as rescue operations.

Phase 2 of the project is set to start very soon. This phase will involve building the interior of the container to resemble a typical residential dwelling.

Stay tuned for more pictures and information as the project continues!